Bathroom to shower room conversion
End of day 1 – Bathroom removed, tiles removed, plasterboard removed, shower stud work removed.
Day 2 – Ceiling plasterboarded, Radiator pipe work moved, new basin waste installed, pipework started for shower valve.
Day 3 and 4. Pipe work moved and concealed to remove any boxing in. Floor repaired and ply lined. Ceiling plastered. Walls lined with tile backer board and shower tray installed.
Completed bathroom.